Our Aluminium Flagpoles

Installation Of One Piece Aluminium Flagpoles With Hinged Baseplates

l. Recommended size of foundation. - see below.

2. Set bolts into concrete with 75 mm. above finished level of foundation. Use bottom half of hinged plate as a template for the position of the bolts. Set bolts into the concrete using a nut at the bottom of the bolt to give an extra key in the concrete.

3. When concrete is hardened (4/5 days), bolt bottom of hinqe plate onto the bases (concrete foundation). Then place four nuts (1 per bolt) loose just above the nuts for the hinge plate.

4. Attach flagpole baseplate to the bottom half of the plate which is now bolted down.

5. Raise flagpole into position. Make flagpole safe with nuts and washers, then use nuts on underside of pole base to screw pole to the vertical. Once achieved, lock off with nuts on topside of baseplate.

Height Metres Foundation Size Depth/Width mm Foundation Stud Length of Stud mm Baseplate Centres mm

5

800/600

M16

500

200 x 200

6

800/600

M16

500

200 x 200

7

1000/600

M16

500

200 x 200

8

1000/800

M16

500

200 x.200

10

1000/800

M20

600

300 x 300

12

1500/1000

M20

600

300 x 300

14

1500/1000

M24

750

300 x 300

16

1500/1000

M24

750

300 x 300